Projects / Case study

Twelve deliverables in four and a half weeks

A subsidiary of a global building-materials group needed a plan to replace its legacy logistics platform, which works alongside its SAP system. The brief asked for twelve deliverables, from a current-state assessment to an executive recommendation, in about four and a half weeks. It was also our company's first discovery of this kind, so we had to build the method while using it. All twelve were finished on time.

My role
Senior Product Manager / Lead Business Analyst, leading the client-facing discovery
Client
CEE subsidiary of a global building-materials group
Team
Four people plus the CTO, at Sonrisa Technologies
Timeline
October to November 2026
  • 12 / 12deliverables completed as version 1.0 and sent with the commercial offer
  • 17client sessions in 15 working days, run with the engineering lead
  • 143legacy platform functions described from the code in the first week
  • 31 / 32open decisions closed in one sitting when the deadline moved

The challenge

A multi-year replacement to plan, on a fixed deadline

The client needed more than a description of today: it needed a programme it could decide on, with stages, costs, risks, a way of working and a clear path to switching the old platform off safely.

  • Twelve deliverables, one deadline. Each came as a report or deck, and where the brief asked for one, a register or model in Excel.
  • No method yet. It was the company's first discovery of this kind.
  • Evidence from the source. What the platform actually does was established from its code and from the people who use it.

The first move

Before writing anything, I defined what "done" meant for every deliverable.

In the first week I turned the client's brief into a deliverable scope document: for each of the twelve, the content, inputs, definition of done, quality gate, format and confidence target. It was accepted on 14 October and guided the team for the rest of the engagement. My colleagues rated it crucial to the project's success, and the retrospective recommends reusing it in every future discovery.

How it ran

From the brief to a programme the client can decide on

  1. Discovery with the client, at pace

    With the engineering lead, I ran 17 client sessions in 15 working days: workshops, interviews and a meeting with the logistics lead. Every session had prepared questions for each function and was followed by a summary memo. Because I had described the platform's functions from the code in the first week, the workshops started from evidence rather than from a blank page.

  2. Backlog, estimate and scope scenarios

    I built the product backlog of work packages and user stories, and the effort estimate and scope scenarios behind the commercial offer and the cost model. The backlog went through 48 controlled changes, and no item that a person had edited was ever overwritten.

  3. The replan when the deadline moved

    The client brought the delivery date forward. I prepared a decision workbook with a recommended choice for every open point, and the team agreed 31 of 32 decisions in one sitting. From then on, every open client question became a stated assumption with its confidence and risk, and I moved the backlog to a fast track: a lighter story format from 29 October, a pilot the next day, four parallel clusters, and the integrated backlog on 2 November.

  4. Finalising the core of the client pack

    With the engineering lead, I finalised the first six deliverables, from the current-state assessment to the phased roadmap and stage gates. I created the solution options assessment on my own, finalised the risk and dependency register through about 29 versions in 15 days, and brought the implementation governance and delivery plan to version 1.0. Then I aligned the format of the whole pack in one pass, fixing 64 format issues.

  5. Turning the project into a reusable asset

    I led the retrospective (23 lessons and a scorecard against the discovery's KPIs) and wrote a client-neutral discovery playbook with 8-week and 6-week reference plans, a quality system and templates, plus a toolkit catalogue. The company now has a tested starting point for its next legacy-modernisation discovery.

Governance and validation

A programme with gates, owners and a definition of ready

The plan the client received is built to be run, not just read:

  • Phased roadmap and stage gates. Every stage has its scope, dependencies, entry and exit criteria, resource plan and cost range.
  • Implementation governance. Programme structure, decision rights, delivery method, quality gates, training, cutover and hypercare.
  • Validation plan. Test strategy and UAT, requirements traceability, data migration validation and go-live readiness criteria.
  • Stage 1 exit scope. What has to be true to switch the old platform off safely: gap list, data migration, cutover, rollback, acceptance criteria and decommissioning.
  • Risk register. Business, technology, security, migration, delivery, supplier and ERP risks, each with an owner and a mitigation.

Who did what

The client pack, and my part in it

This was a team effort, so here is exactly where my work sits. I finalised eight of the twelve deliverables, six of them together with the engineering lead, and created one on my own.

The twelve deliverables
#DeliverableWhat it coversMy part
D1Current-State AssessmentProcesses, interfaces, data, technical debt and pain points of the legacy platform, verified against its codeFinalised with the engineering lead, with input from the AI team lead
D2Target Capability ModelThe end-state business capabilities, from what is needed to switch the old platform off to strategic onesFinalised with the engineering lead, with input from the AI team lead
D3Solution Options AssessmentBuild new, reuse or buy, scored against agreed criteria, with a recommendationCreated on my own; reviewed by the head of consultancy
D4Architecture PackCurrent, transition and target architecture, including the ERP boundary, integrations, data and securityFinalised with the engineering lead, with input from the AI team lead
D5Stage 1 Exit DefinitionGap list, data migration, cutover, rollback, acceptance criteria and decommissioningFinalised with the engineering lead, with input from the AI team lead
D6Phased Roadmap and Stage GatesStages, dependencies, entry and exit criteria, resource plan and cost range per stageFinalised with the engineering lead, with input from the AI team lead
D7Target Operating ModelOwnership, support levels and sourcing scenarios for the new platformClient-pack format and consistency
D8Cost and TCO ModelOne-off and running costs per stage, in three scenariosBuilt the backlog and estimate that feed it
D9Benefits and KPI ModelBaselines, targets and how benefits will be measuredStarted it: the KPI catalogue
D10Risk and Dependency RegisterA live register of business, technology, migration, delivery, supplier and ERP risksStarted and finalised it: about 29 versions in 15 days
D11Implementation Governance and Delivery PlanProgramme structure, decision rights, quality gates, testing, training, cutover and hypercareBrought it to version 1.0, including the validation plan
D12Executive RecommendationThe decision paper for the client's executive committeeClient-pack format and consistency

AI-enabled delivery

Claude Code on a repository of legacy code

The team worked in a shared Git repository holding the legacy code and its documentation. I used Claude Code to describe the platform's functions from the code in the first week, and built reusable AI skills for the steps we repeated: workshop preparation, summary memos, the backlog, the estimate and the scope scenarios. The team rated the memos reliable enough to need little checking. Together with the engineering lead and another team member, I created the cross-validation methodology that checked all twelve deliverables for accuracy and for consistency with the rest of the pack. My own addition was checking that every document matched the company style guide. To keep formatting consistent, I harmonised the build pipelines for Word, Excel and PowerPoint documents: I built a standardised toolset that produces all three from Markdown source files. With 162 commits, I made the most on the team.

Outcome

All twelve deliverables, on time

All twelve deliverables were completed as version 1.0 on 11 November 2026, and the pack went to the client with the commercial offer the next day.

What I'm taking forward

Check early, keep one source of truth

Under a fixed deadline, checking came too late and money figures lived in more than one place, and both caused rework. The playbook turns this into practice for next time:

  • One source for all figures, with the estimating method fixed in the first week.
  • A light automated check on every build of the deliverables.
  • Gates set from the workshop calendar, so reviews happen while there is still time to act on them.

Client details are confidential, so names of the client, its group and its systems are left out.